Factory operations / Reconfiguration plan
Factory reconfiguration
CNC 1 | VMC | CNC 2Assembly, wiring and software hand-offs.
PLANNING WINDOW
06 – 20 October 2026
The hand-off sequence
CNCs moved
and aligned
and aligned
Gantry base
sub-assembly
sub-assembly
Full assembly
+ rails + rack
+ rails + rack
Gantry + end-
effector wiring
effector wiring
Motor tuning
one full day
one full day
Hardware ready
software starts
software starts
Physical software testing starts Oct 14. Codebase checks run Oct 6–10. Pose setup and pick-and-place wait for floor arrangement, gantry assembly, wiring and tuning.
VMC expected Oct 14–20. No VMC poses are scheduled. AMR mapping, navigation and docking follow final placement; they do not have a fixed Oct 20 deadline.
Workstreams
Scroll sideways to see the full Oct 6–20 timeline.
All dates are in October 2026. Hover over a row or bar for task details.
ScheduledOptional / if neededDelivery / required parts
MechanicalElectricalSoftwareConstruction
Deadlines are target dates. Unscheduled dependencies stay undated.Assembly controls the start
Main assembly starts Oct 8 once the required parts are ready. Complete assembly, guide rails and rack gear by Oct 10; only then start gantry and end-effector wiring.
Existing machines vs. incoming VMC
The Oct 10 machine-wiring and earthing deadline covers the existing CNCs. Stabilizer installation assumes arrival Oct 9 or 10. VMC utilities follow delivery and placement.
Ordering is not delivery
Tooling, fixtures, probe and motor dates are order-placement deadlines. Acrylic changes and FOCAS are optional; camera calibration and inspection-backend changes are only if required.